[Home]  [Notice]  [Environment]  [Services]  [Case studies]  [Experience]  [Project Finance Experience]  [Profile]  [FAQ's]  [Contact]  [Feedback]  [Links]  [Site Map]

Tynagh Energy CCGT Power Plant

Gama Construction Ireland Limited

Copyright in picture owned by Tynagh Energy Limited / Gama Holding

Summary

In December 2003, Talanworth was hired to provide project finance advisory services to Gama, an international construction company headquartered in Ankara, Turkey.

Talanworth worked as an integral member of the project team to achieve preferred bidder status and to finance the construction of a new 400MW combined cycle gas turbine power generation project costing in excess of €250m.  In early 2004 the Talanworth mandate was extended to provide financial modelling services to the project company on a sub-contracted basis.

Talanworth’s role included also management advice in discussions with the lead arranging banking group and managing tax, accounting and insurance advisers.

The project is being developed under an Implementation Agreement entered into between the Commission for Energy Regulation in the Republic of Ireland (CER) and Tynagh Energy Limited, majority owned by Gama Construction Ireland. To see the latest status use this link: Current Status

Tynagh Energy Limited achieved financial close on 27 August 2004.  The project is currently under construction at Derryfrench, Tynagh, County Galway, Ireland.

Detail

Project Rationale and background

The Commission for Energy Regulation (CER) is the independent body responsible for regulating and overseeing the liberalisation of Ireland ’s energy sector. The CER’s powers are specified in the Electricity Regulation Act, 1999 and the Gas (Interim) (Regulation) Act, 2002. ESB National Grid, in its Generation Adequacy Report (2003-2009), identified significant generation shortfalls from 2003 to 2009 as forecasted demand for electricity continues to grow (approximately 3.5% p.a. for the period). ESB National Grid identified electricity generation shortfalls of approximately 150MW in 2003, 300MW in both 2004 and 2005, growing to 360MW in 2006 with further increases in future years.

In response to the Generation Adequacy Report and in light of its duty to promote security of supply, the CER initiated a number of measures to increase generation capacity in Ireland.  As construction of new generation plant requires a minimum of two years, the CER established a project to address the projected shortfalls in the interim period involving demand-side and generation-side initiatives. This three-pronged approach consists of demand side management (DSM) measures, increased imports from Northern Ireland and the installation of temporary generation.

In February 2003, the Commission announced its intention to hold a competition to facilitate the entry of new independent generation plant in Ireland to address the projected shortfall in generation capacity in 2005 as identified by ESB National Grid. In April 2003, Guidelines to the Competition were published, requesting potential bidders to submit an expression of interest in the competition. The CER received valid Expressions of Interest from seven generators interested in bidding into the competition with a combined generating capacity of 2,185 MW.

The CER issued to the seven generators an Invitation to Tender dated 22 May 2003 was amended 15 July 2003 and revised and reissued on 28 August 2004 inviting the seven generators to submit a tender by 20 October 2003 with a maximum contractual capacity up to 531MW.  Tynagh Joint Venture, including Gama Construction Ireland Limited, (Gama Ireland), submitted such a tender.  The ITT is available online on the CER’s web site as CER/03/166 and the Implementation Agreement as proposed in such ITT as CER/03/165.

On 4th December 2003, Gama Ireland appointed Talanworth to support it in the preferred bidder negotiations with CER. Tynagh Energy Limited was formed to enter into the project documents.

Preferred Bidder

On 24 December 2003 the CER announced: “that both Aughinish Alumina and Tynagh Energy Ltd. have been successful in the competition it facilitated to promote the entry of new generation plant(s) into Ireland. The combined installed generating capacity of these two new independent generating plants is over 500 MW.

The winners have each secured a contract with ESB and the combined potential value of these contracts is over €1.5 billion.

Bidders competed for the contracts on the basis of price, after having met a number of outlined minimum qualification requirements, which included technical, financial and regulatory criteria.

Both successful bidders have signed Capacity Contracts with ESB for up to ten years as well as grid connection agreements with ESB National Grid. Furthermore both parties have signed Implementation Agreements with the CER and put commitment bonds in place to ensure the speedy construction of the plants.”

Financing

The details of the finance structure are confidential but include both senior and mezzanine debt supported by shareholder finance. Flexibility in the repayment term is provided and the lenders and insurers active support has enabled enhanced technology to be incorporated into the project.

Talanworth’s role for Tynagh Energy Limited included hiring a power project financial modelling company to develop a financial model used to assist in the finance structure and commercial development of the project.  This role included supporting the development of a streamlined financial model developed by the lead arranging banks used for the banking base case and for syndication of the debt facilities and since adopted as the Project Model.

For Gama Ireland, Talanworth assisted in the review of the main project documents and participated as required in the negotiation of the Equipment Procurement and Construction Contract with General Electric and Gama affiliates, and the Operation and Maintenance Contract and Gas Supply & Tolling Contracts with separate RWE affiliates.

Financing support included the detailed review and advice to Gama on each of the finance and security documents, covering negotiations on the term sheets and loan agreements with the lead arrangers for both senior and mezzanine debt. Talanworth also negotiated the appointment of insurance and tax and accounting advisers and managed such advisers.  A full Owner Controlled Insurance Programme was established to address supply, shipping, erection and construction with also protection for environmental liability. 

Nigel Hawke worked as an integral member of the Project Team, based in Ireland, and provided on -going financial management support. This extended to support to Gama for complex sponsor support arranged for certain aspects of the financing.  The objective throughout was a balanced risk return relationship to control the sponsor’s exposure to the project.

Financial close was achieved on 27 August 2004.

Corporate Support

Talanworth also provided regular reports to the senior management of Gama detailing the development of the project and how the risk allocation amongst the parties was being managed.  This included devising solutions to issues as they arose, a role with which Nigel Hawke is very familiar in other comparable roles.

By involving Talanworth at such a level senior management obtain additional experienced resource with their best interests in mind and timely advice on the issues that need to be addressed without having to commit long-term or to incur direct employment expense.

Nigel Hawke also assisted the Project Company to recruit for the role of de-facto Finance Director and drew up the job specification, interviewed and briefed candidates and coached the successful candidate both before and once formally appointed to the role of Senior Finance Manager.  Prior to such person being appointed the Project Company Management Accountant was also guided and supported by Nigel.

The project company’s Management Plan was developed by Talanworth from principles laid down by Gama about how the project company should managed and the Board of Directors organised.

Construction

Construction commenced early in 2004 and the power generation facility will come into operation within less than two years.  The construction consortium comprises General Electric affiliates and Gama Power Systems Inc. an affiliate of Gama, acting jointly and severally. General Electric is one of the world leading companies in power generation and Gama is very experienced with such construction having been a contractor for the 343 MW CCGT Huntsdown Power Station in Ireland, the 4 x 360 MW Afsin-Elbistan B Thermal Power Plant, Turkey, the 2 x 660 MW Iskenderun Soguzu Thermal Power Plant, Turkey, the 5 x 367 MW Shoaiba Thermal Power Plant, Saudi Arabia, and the 6 x 112 MW hydro-electric plant at Birecik, Turkey which are selected recent power plant construction projects.

Operation

The facility will be operated for Tynagh Energy by an affiliate of RWE and fuel will be supplied by another affiliate of RWE. The State Electricity Supply Board is providing an capacity and differences agreement which provides the facility with a guaranteed income, subject to meeting availability standards and other obligations, as more particularly described in the ITT and in other documents on the CER’s own web site.  Tynagh Energy also contracted the remaining available capacity.

General Electric affiliates will support the heavy maintenance of the gas and steam turbines and  the generators for an initial period.

Bord Gais will construct a 16km gas pipeline and ESB via its contracting arm will construct a 2 km overhead line. Water will be supplied from a neighbouring site.

Sponsors

Gama Holdings AS, headquartered in Ankara, Turkey, is the top company of the Gama group established in 2003 following a restructuring of the group into five core functions: Industry, Power Systems, International, Energy and Trade & Tourism.

The origins of the group date back to 1959 when the civil construction business was inaugurated,  which was expanded during the 1980’s into the Middle East, Russia, the CIS countries, Southeast Asia, North Africa and Europe.  Activities encompass turnkey construction of industrial plants, power generation plants and pipelines, office towers, dams, commercial centres and housing complexes, highways and bridges. 

Group turnover was USD 437 million in 2003, with on-going construction contracts of USD 1.2 billion, of which Ireland accounts for 38%, Turkey 28% and Saudi Arabia 18%. Order backlog amounted to USD 611 million. All figures as at 31 December 2003 .

Gama Industry specialises in the construction of industrial facilities, including thermal power plants, refineries, petrochemical plants, hydroelectric power plants, water and waste water treatment plants, cement factories and pipelines, office towers, business and shopping complexes, residential and hotel buildings, social and cultural facilities, health facilities, dams, underground transportation systems and utilities and the installation of mechanical & electrical equipment and instrumentation. This part of the group also owns a steel construction and boiler manufacturing plant and has investments in real estate and cement production.

Gama Power Systems is the leader in the group for engineering, supply and turnkey construction of power plants both in its domestic markets and overseas.  This grew out of a highly successful design, supply, fabrication, installation, operation and maintenance of steam boilers since 1963.

Gama International provides an umbrella organisation for the groups leading overseas operations with subsidiaries in Ireland, Bulgaria and Saudi Arabia. 

Gama Construction Ireland has increased its volume of business in excess of USD 350 million, with projects including the 100 MW Lough Ree Power Plant, Lanesborough, Balgaddy A-8 and B-Phase Housing Projects (149 residences),  Ballymun Coultry-3 Housing (87 units), Blanchardstown 72 residences, and Ballincollig Bypass motorway project – second largest Irish motorway construction. Projects in course in Ireland include 150 MW West Ofally, Shammonbridge – power plant site arrangement and building construction works, Project C, D & E Balgaddy (314 homes/residences plus commercial and community buildings), 164 Balcurris residences, Ballymun, 220kv Corduff Transformer Station, 3,800 m2 Northwood Office Building, Santry, Dublin and the Tynagh Energy power plant in Galway.

Gama Energy has investments in the Izmit Domestic and Industrial Water Supply Project, Turkey, the Trakya Power 478 MW CCGT Marmara Ereglisi power plant, Turkey, the TGT Power 153 MW Kirikkale Power Plant, Turkey and the 672MW Birecik Dam hydro-electric power plant, Turkey.

Gama Trade and Tourism has marketing and commercial activities in medical products (internal orthopaedic prosthetics and orthopaedic products), domestic and overseas trade (industrial flow metres, ductile pipes, & fittings, marketing of cables, building chemicals, insulation materials, fuel and mineral oil), office equipment sales and after-sales services, maintenance and repair services, and also insurance.  This sector also operates the Renaissance Antalya Beach Resort & Spa Hotel, Turkey owned by the Marriott Group.

Mountside Properties Limited, a minority owner of Tynagh Energy Limited is a property development company formed specifically to obtain the site for the Tynagh project and to assist in project development.

© Copyright Talanworth Limited 2004 - 2011